Louisiana is about to decide something bigger than one data center.
- Entergy Louisiana disclosed on 7 October that Meta’s Hyperion campus needs 4,500 megawatts, four times the peak load of New Orleans and about twice the demand of the utility’s other customers in the state.
- The figure had been sitting in a MISO interconnection report since 8 September. It became public only under questioning at a hearing of the Public Service Commission.
- Seven gas units of 453 megawatts each are moving through a fast track that skips market analysis and competitive bidding, with much of the record marked confidential.
- Ten new gas generators will serve the one campus, including three units 150 miles away linked by a proposed 500 kilovolt line.
- The commission is expected to vote later this year. Other states face the same question about who approves a load this size and who pays for the wire.
Why the process matters more than the megawatts is in the full analysis.
Get the next one before it is old news
Independent analysis of cloud-native infrastructure, Kubernetes and data center economics. No vendor spin.